The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to ... power plant were necessary. The regulator’s two Republican commissioners ...
Nuclear-power stocks slumped on Monday after US regulators barred a plant from supplying extra power to an Amazon data center. The Federal Energy Regulatory Commission rejected the deal between ...
Talen Energy and other US power company stocks slumped Monday following the rejection by the country’s top energy regulator of Talen ... of power supplied to an Amazon.com data facility ...
(Bloomberg) -- Amazon.com Inc. said it’s committed to building a data center campus adjacent to a Pennsylvania nuclear plant after the top US energy regulator rejected a special deal to power ...
Talen Energy Corp. says Amazon has planned up to 960 ... But the energy regulator's commissioners voted 2-1 to reject the deal, finding that the applicants “failed to meet the high burden ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to ... power plant ...
Nuclear-power stocks slumped on Monday after US regulators barred a plant from supplying extra power to an Amazon data center. The Federal Energy Regulatory Commission rejected the deal between Amazon ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into additional ... agreement with Susquehanna power plant were necessary. The regulator ...